The Hornsea One Pre Assembly Project based on the north bank of the Humber is now well and truly underway!
Our Windhoist team, led by experienced Site Manager Eddie Wilson, are now fully mobilised and have to date erected the first tower. We plan to have the first load out fully upended this weekend which leaves 20 towers to upend before the end of the year!
The project is for 174 turbines which are 7MW each. That is a lot of energy!
Recently the team participated in a 3-day behavioural safety event which focused on team development and site safety. This training has helped strengthen and further develop the safety culture we strive to embed into the project and we would like to thank all of those who participated for their positive engagement.
In addition, thank you to SGRE Site Manager Michael Shultz for the photographs taken whilst the first tower section was being upended and for the positive feedback below: