Moving our LTR11200 from Hallett Windfarm to Hallett Hill Windfarm (Hallett Stage 2)undertook the re-location of all the heavy loads, heaviest of which was the bottom superstructure which weighed 64T.

Local haulier Peter Fitzgerald also assisted by transporting all the standard loads.

We started moving out on Monday morning 21/11 and had the crane rigged up again ready to lift on Wednesday afternoon 23/11.

Total of 296T of equipment moved. As there was some very steep hills on both sites local farmers Darren Robinson and Will Gebhart helped to tow the heavy loads with there large tractors. Both tractors we 500hp+.

We are working for Suzlon energy Australia changing generators on their S88 turbines. We have just completed 16 changes at Hallett windfarm and have another 30 to do at Hallett hill.